Germany: onshore wind permitting-to-grid capacity bottlenecks
=============================================================

**News trigger:** Reuters, 6 November 2026, reported German onshore wind
transport delays and grid connection constraints despite record approvals.
https://www.reuters.com/business/energy/germanys-onshore-wind-boom-faces-logistical-hurdles-turbine-orders-surge-2026-11-06/

**Business question:** For already-approved onshore wind projects, which
annual throughput expansion unlocks commissioning: transport, erection or grid?

**Observed published aggregates** (not individual project time series): German
industry/Fachagentur Wind und Solar reported 48.1 GW approved but not operating
as of 30 June 2026, with about 19 GW still without auction awards. Sources and
caveats: :doc:`onshore logistics scenario guide
</_generated/guides/germany-wind-logistics>`.

**ILLUSTRATIVE hypothetical assumptions:** annual transport, erection, awards
and grid throughput rates; zero new approvals to isolate that historical cohort.
This is NOT a 2027-2032 forecast. See the documentation for provenance and
boundary conditions. Runs offline and uses no downloaded copyrighted tables.
"""

# %%
# Published sources anchor the size of the approved cohort only.
import matplotlib.pyplot as plt
import numpy as np

from energy_methods.wind_pipeline import simulate_wind_pipeline

SOURCE_PIPELINE_GW = 48.1
SOURCE_UNAWARDED_GW = 19.0
SOURCE_AS_OF = "2026-06-30"
SYNTHETIC_YEARS = tuple(range(2027, 2033))


def scenario(*, transport_gw: float, grid_gw: float):
    """Hypothetical annual throughput scenario, not calibrated to Germany."""
    return simulate_wind_pipeline(
        first_year=SYNTHETIC_YEARS[0],
        initial_unawarded_gw=SOURCE_UNAWARDED_GW,
        initial_awarded_gw=SOURCE_PIPELINE_GW - SOURCE_UNAWARDED_GW,
        new_approvals_gw=(0.0,) * len(SYNTHETIC_YEARS),
        awards_per_year_gw=15.0,  # invented scenario, not 2027 auction realization
        transport_per_year_gw=transport_gw,
        erection_per_year_gw=12.0,
        grid_per_year_gw=grid_gw,
    )


# %%
# Paired sensitivity: changes only in transport and/or grid throughput.
cases = {
    "Baseline: 6 GW transport / 7 GW grid": scenario(transport_gw=6, grid_gw=7),
    "Transport expansion: 11 / 7": scenario(transport_gw=11, grid_gw=7),
    "Grid expansion: 6 / 12": scenario(transport_gw=6, grid_gw=12),
    "Both expansions: 11 / 12": scenario(transport_gw=11, grid_gw=12),
}

for name, values in cases.items():
    end = values[-1]
    print(
        f"SYNTHETIC {name}: commissioned={end.cumulative_commissioned_gw:.1f} GW, "
        f"awaiting award={end.waiting_for_award_gw:.1f} GW, "
        f"awaiting transport={end.waiting_for_transport_gw:.1f} GW, "
        f"awaiting erection={end.waiting_for_erection_gw:.1f} GW, "
        f"awaiting grid={end.waiting_for_grid_gw:.1f} GW"
    )

fig, ax = plt.subplots(figsize=(10, 5), layout="constrained")
for name, result in cases.items():
    ax.plot(
        SYNTHETIC_YEARS,
        [row.cumulative_commissioned_gw for row in result],
        marker="o",
        label=name,
    )
ax.axhline(SOURCE_PIPELINE_GW, ls="--", color="gray", label="Published approved stock")
ax.set(
    title="Germany onshore: HYPOTHETICAL bottleneck capacity scenarios",
    xlabel="Illustrative calendar year (no project-level timing calibration)",
    ylabel="Cumulative commissioned GW from June 2026 cohort",
    ylim=(0, SOURCE_PIPELINE_GW * 1.12),
)
ax.legend(fontsize=8)
plt.show()

# %%
# Two-dimensional bottleneck surface: a larger construction throughput alone
# cannot overcome a smaller capacity at another mandatory stage.
transport_values = np.array([4, 6, 8, 10, 12, 14], dtype=float)
grid_values = np.array([4, 6, 8, 10, 12, 14], dtype=float)
commissioned = np.array(
    [
        [
            scenario(transport_gw=float(t), grid_gw=float(g))[-1].cumulative_commissioned_gw
            for t in transport_values
        ]
        for g in grid_values
    ]
)
fig, ax = plt.subplots(figsize=(8, 6), layout="constrained")
heatmap = ax.imshow(commissioned, origin="lower", cmap="viridis", vmin=0, vmax=SOURCE_PIPELINE_GW)
ax.set_xticks(range(len(transport_values)), [str(int(t)) for t in transport_values])
ax.set_yticks(range(len(grid_values)), [str(int(g)) for g in grid_values])
ax.set(
    title="ILLUSTRATIVE 6-year delivery vs logistics and grid limits",
    xlabel="Annual turbine transportation throughput (GW/year)",
    ylabel="Annual grid connection throughput (GW/year)",
)
for row in range(len(grid_values)):
    for column in range(len(transport_values)):
        ax.text(
            column,
            row,
            f"{commissioned[row, column]:.1f}",
            ha="center",
            va="center",
            color="white",
            fontsize=8,
        )
fig.colorbar(heatmap, ax=ax, label="Cumulative connected wind capacity (GW)")
plt.show()

# %%
# Model controls and limitations: optimistic within-year flow through stages,
# aggregated national stocks, no actual projects, weather, permits, cancellations,
# financing, location-specific access roads, line upgrades or energy output.
# 2025 annual approval/installation values are independent cohorts and MUST NOT
# be subtracted to infer project-level conversion times.