Dogger Bank C: offshore installation-vessel capacity and grid readiness
=========================================================================

**Dated primary evidence:** Dogger Bank Wind Farm, 4 November 2026, announced
that Wind Apex is expected to join Seaway Ventus for Dogger Bank C in Q3 2027.
Phase C has **87 turbines and 1.2 GW**. These are public project announcements,
NOT measured work rates, actual site conditions, or an operating forecast.
Source: https://doggerbank.com/news/

**Business question:** How might a second installation vessel change the
construction critical path and the *opportunity* for eventual renewable energy?

The daily planning method represents a common site-weather gate and
per-vessel work-days-per-turbine, followed by a separate grid-ready gate.
This exercise uses **SYNTHETIC** weather and **ILLUSTRATIVE** time, efficiency,
capacity factor and price assumptions. It estimates neither the real Dogger
Bank schedule nor an economic value agreed by the developer. Run entirely
offline; no licensed generation data or API credentials are needed.

See :doc:`source facts, formulas and scientific limits
</_generated/guides/offshore-installation-vessels>`.
"""

from __future__ import annotations

import random

import matplotlib.pyplot as plt
import numpy as np

from energy_methods.wind_installation import (
    commissioning_opportunity_mwh,
    simulate_installation,
)

# %%
# 1. Separate dated source facts from uncalibrated scenario inputs
# -------------------------------------------------------------------
# News-reported project scope, NOT a dataset of operational measurements:
PHASE_TURBINES = 87
PHASE_CAPACITY_MW = 1200.0
SOURCE_FACTS = {
    "turbines": PHASE_TURBINES,
    "capacity_mw": PHASE_CAPACITY_MW,
    "second_vessel_arrival_window": "Q3 2027",  # do NOT infer an exact date
    "published_on": "2026-11-04",
    "source": "https://doggerbank.com/news/",
}

# Illustrative assumptions below are NOT from the press release. Day zero is an
# arbitrary campaign start, not a claimed Dogger Bank commissioning date.
DAYS = 560
SECOND_VESSEL_DAY = 90
WORKABLE_DAY_PROBABILITY = 0.70
WORKABLE_DAYS_PER_TURBINE = 3.0
NET_CAPACITY_FACTOR = 0.48
ASSUMED_PRICE_EUR_MWH = 65.0
ENSEMBLE_SEED = 20261107
ENSEMBLE_SIZE = 200


def weather_scenario(seed: int) -> list[bool]:
    """Independent synthetic Bernoulli workability per day; no site calibration."""
    generator = random.Random(seed)
    return [generator.random() < WORKABLE_DAY_PROBABILITY for _ in range(DAYS)]


# %%
# 2. Compare paired schedules with identical illustrative weather
# ------------------------------------------------------------------
# Common random weather is used in both alternatives to isolate vessel count.
# Uncertainty bands represent variation under this invented weather law,
# NOT probabilities about actual Dogger Bank construction.
scenarios = []
for run in range(ENSEMBLE_SIZE):
    workable = weather_scenario(ENSEMBLE_SEED + run)
    baseline = simulate_installation(
        PHASE_TURBINES,
        vessel_start_days=(0,),
        workable_days=workable,
        workable_days_per_turbine=WORKABLE_DAYS_PER_TURBINE,
    )
    second_vessel = simulate_installation(
        PHASE_TURBINES,
        vessel_start_days=(0, SECOND_VESSEL_DAY),
        workable_days=workable,
        workable_days_per_turbine=WORKABLE_DAYS_PER_TURBINE,
    )
    scenarios.append((baseline, second_vessel))

one_vessel_days = np.array([a.duration_days for a, _ in scenarios])
two_vessel_days = np.array([b.duration_days for _, b in scenarios])
saved_days = one_vessel_days - two_vessel_days

print("SOURCE FACTS (project announcement):", SOURCE_FACTS)
print("SYNTHETIC assumptions: 70% daily workability; 3 workable days/turbine")
print("SYNTHETIC arrival offset: 90 campaign days (not Q3 start-date inference)")
print("SYNTHETIC one-vessel median completion:", float(np.median(one_vessel_days)))
print("SYNTHETIC two-vessel median completion:", float(np.median(two_vessel_days)))
print("SYNTHETIC saved campaign days, P10/P50/P90:", np.percentile(saved_days, [10, 50, 90]))

fig, ax = plt.subplots(figsize=(8.5, 4.5), layout="constrained")
ax.hist(one_vessel_days, bins=20, alpha=0.6, label="1 vessel")
ax.hist(two_vessel_days, bins=20, alpha=0.6, label="2 vessels (second at day 90)")
ax.set(
    title="Dogger Bank C — SYNTHETIC construction scheduling sensitivity",
    xlabel="Illustrative campaign day of final installation",
    ylabel="Number of synthetic scenarios",
)
ax.legend()
plt.show()

# %%
# 3. Grid-connection sensitivity: what if completion is not the critical path?
# -------------------------------------------------------------------------------
# Potential generation assumes each equal-rated turbine can export no earlier
# than the day after installation plus a common grid-ready date; constant net
# capacity factor is illustrative. Grid readiness at day 350 can erase much
# of the benefit of accelerating installation if both finish beforehand.

fig, ax = plt.subplots(figsize=(8.5, 4.5), layout="constrained")
for grid_ready_day in (0, 350, 500):
    energy_advantages = []
    for one, two in scenarios:
        params = dict(
            project_capacity_mw=PHASE_CAPACITY_MW,
            net_capacity_factor=NET_CAPACITY_FACTOR,
            horizon_days=DAYS,
            grid_ready_day=grid_ready_day,
        )
        one_mwh = commissioning_opportunity_mwh(one, **params)
        two_mwh = commissioning_opportunity_mwh(two, **params)
        energy_advantages.append(max(0.0, two_mwh - one_mwh))
    low, middle, high = np.percentile(energy_advantages, [10, 50, 90])
    print(
        f"ILLUSTRATIVE grid-ready day {grid_ready_day}: additional energy opportunity "
        f"P10/P50/P90 {low:,.0f}/{middle:,.0f}/{high:,.0f} MWh; "
        f"median gross value at a HYPOTHETICAL €65/MWh: "
        f"€{middle * ASSUMED_PRICE_EUR_MWH:,.0f}"
    )
    ax.errorbar(
        grid_ready_day,
        middle,
        yerr=[[middle - low], [high - middle]],
        marker="o",
        capsize=5,
        label=f"Grid day {grid_ready_day}",
    )
ax.set(
    title="Additional modeled energy opportunity, NOT actual generation or revenue",
    xlabel="SYNTHETIC common grid-ready campaign day",
    ylabel="Additional potential exported energy by day 560 (MWh)",
)
ax.set_xlim(-45, 545)
ax.grid(alpha=0.2)
plt.show()

# %%
# The plotted P10/P90 intervals ONLY reflect the invented independent-day
# weather process. They are not a confidence interval for this project.
# This model excludes port/logistics, foundation readiness, vessel capabilities,
# turbine-specific ratings, cable commissioning, contractual delay penalties,
# downtime correlation, electricity market prices and O&M costs. A real
# financial case requires validated site progress, metocean and grid schedules.