Portugal 2026 BESS connection auctions — power and energy screening#

Evidence, dates and decision#

Business question: What inverter rating and nominal storage-energy envelope should a developer investigate before bidding for Portugal’s October 2026 grid-connection auctions?

The official DGEG standalone auction specifies up to 750 MVA of apparent-power grid injection access, BESS power at least 100% of the awarded capacity and at least four hours at maximum injection power (Order 12924-C/2026, 22 October).

The official DGEG renewable co-located auction offers 300 MVA of access; BESS power is at least 20% of awarded injection and the DGEG summary also says four hours at maximum injection power (Order 12924-B/2026, 22 October). The government announcement is dated 27 October.

The 9 November news report describes a 50 MVA minimum application and 22 December 2026 deadline. Primary regulator and government evidence is distinguished from secondary reporting in the dated JSON snapshot. None of these figures is a measured generation or battery dispatch record.

Method and physical baseline#

The pure-Python function energy_methods.portugal_storage_auction.screen_portugal_storage_auction produces a conditional engineering design envelope, rather than treating MVA as though it were MW.

  1. Apparent versus active power: P_export_MW = S_awarded_MVA × assumed_active_power_factor. Power factor is a scenario input, not a tender parameter independently verified here. Physical P-Q capabilities, inverter guarantees and the interpretation of nameplate MVA need grid studies.

  2. BESS inverter power: Standalone minimum power screen P_BESS = 1.0 × P_export; co-located minimum-power screen P_BESS = 0.2 × P_export. These are dimensional first approximations for the respective auction fractions.

  3. Delivered energy: E_battery_four_hours = P_BESS × 4h. For the co-located case, report a separate conservative E_full_injection_four_hours = P_export × 4h because DGEG describes four hours at maximum injection power. A 20%-rated BESS inverter does not deliver full export power for four hours; these cases cannot be substituted for checking the binding tender programme.

  4. Nominal energy at end of life: E_nameplate = E_delivered / (AC_discharge_efficiency × EOL_usable_fraction). The illustrative 94% AC discharge efficiency and 80% end-of-life usable fraction are independent engineering assumptions, not measured efficiencies or battery supplier warranties.

For a 50 MVA, power-factor=1 standalone hypothetical bid, 50 MW AC and 200 MWh delivered require approximately 266 MWh nominal under the stated assumptions. For a 50 MVA co-located hypothetical bid, the 20% inverter pre-screen is 10 MW and 40 MWh delivered, requiring around 53 MWh nominal. However, its stricter full-injection stress requires 50 MW and 200 MWh delivered, equivalent to about 266 MWh nominal. This is an interpretation stress comparison, not a legal determination that either is the tender minimum.

Reproduce#

uv sync --locked --all-packages --group docs --python 3.13
uv run --no-sync python examples/analysis/plot_portugal_storage_auction_2026.py
uv run --no-sync pytest methods/tests/test_portugal_storage_auction.py
uv run --no-sync ruff format --check .
uv run --no-sync ruff check .
uv run --no-sync ty check
uv run --no-sync sphinx-build -W --keep-going -b html docs docs/_build/html

The executable gallery reads the source snapshot offline and charts 50/100/200 MVA candidate requests and power-factor sensitivity (0.90, 0.95, 1.00). There are no synthetic time series impersonating measured observations; efficiency and capacity assumptions are explicitly labelled as hypothetical. The zero-loss theoretical balance is the physical baseline. Values are deterministic sensitivities, not confidence intervals.

Limits and next due-diligence steps#

The screen does not establish auction eligibility, individual connection-node capacity, charging capacity, payment/municipal guarantees, grid-forming performance, licensing compliance, debt service, bidding prices, land availability, degradation curves or project economics. In particular, check the full DGEG tender specifications for maximum-injection duration and bid terms, and verify every physical capacity against connection-node restrictions. Neither model nor source snapshot establishes that an auction award or project installation has occurred.