Egypt Niat and Rasgha — wind finance and energy-yield screening#

News trigger: Reuters, 9 November 2026, Alcazar Energy secures $436 million financing for Egyptian wind farms.

Decision question: How sensitive is the bankability of a proposed contracted wind project to yield, electricity tariff, financing and annual operating costs? The study screens the combined 500 MW Niat/Rasgha project and identifies which missing inputs must be obtained before serious investment due diligence.

Dated public-source evidence (not metered or independently audited)#

Source and disclosure

Capacity

Annual generation

Published project cost

Aggregate financing

Indicative price

Reuters, Nov 9

500 MW

More than 2.3 TWh forecast

$626m

$436m debt

$0.03/kWh reported

DEG, Oct 22

500 MW

More than 2.3 TWh forecast

Approx. $580m

Approx. $437m total three-lender financing

Not disclosed

EIB, May 5

500 MW

Not listed on summary

Approx. $572m

EIB component only (proposed ~$152m), not aggregate debt

Not disclosed

Different sources and dates do not establish that project costs changed by a given amount: cost basis, tax treatment, financing scope and revisions are unresolved. The EIB project summary explicitly presents indicative data. The sources do not disclose an audited production dataset, detailed O&M budget, finalized amortization schedule, project cash flow or exact effective electricity-delivery terms. All individual facts and links are also preserved in ras_ghareb_wind_2026.json. This is a static attributed news snapshot, not a live API connector or an observed time series.

Reusable numerical model and checks#

The pure-Python screen_wind_project calculates:

  • Implied net capacity factor: annual_delivered_MWh / (rated_MW * 8,760 h); the stated >2.3 TWh implies >52.5%, a strictly lower bound if the disclosure uses net delivered AC output and 500 MW has a matching basis. Nameplate and forecast boundaries have not been independently confirmed.

  • Illustrative flat nominal PPA gross revenue: delivered_MWh * assumed_USD_per_MWh. At \(30/MWh and the 2.3 TWh boundary, revenue would exceed \)69 million/year if all delivery is paid at that price. It does not establish contracted revenues.

  • Leverage: aggregate reported senior debt divided by same-source project cost, where the source includes both. Do not mix EIB’s proposed component with total debt.

  • Level fully-amortizing annual payment: P*r / (1-(1+r)^(-n)), with an exact zero-interest branch. There are no published rates or repayment dates in the cited sources, so 6% / 15 years is illustrative.

  • Cash-cover screen: (gross_PPA_revenue - assumed_annual_OPEX) / hypothetical_annual_debt_payment. The OPEX baseline of $35/kW-year is an illustrative user assumption, not Egyptian project evidence. This is not a bank DSCR: it excludes taxes, insurance, reserve accounts, cash waterfalls, transaction expenses, FX, escalation and financial covenants.

A ratio exceeding one in this crude screen is not evidence of creditworthiness. The tool validates positive installed power, finite inputs, generation below a nameplate-year ceiling, a bounded rate/tenor and aggregate debt not exceeding capex. Tests cover independent hand calculations, one-year amortization, zero debt, monotonic price/rate sensitivity, the reported news lower bound and invalid inputs.

Runnable analysis and interpretation#

uv sync --locked --all-packages --group docs --python 3.13
uv run --no-sync pytest methods/tests/test_wind_project_finance.py tests/test_gallery_navigation.py
uv run --no-sync python examples/analysis/plot_ras_ghareb_wind_finance.py
uv run --no-sync sphinx-build -W --keep-going -b html docs docs/_build/html

The executable example consumes the dated JSON snapshot offline, reports source-derived algebraic lower bounds, compares non-probabilistic capacity-factor/interest-rate sensitivities, and plots each dated cost estimate separately. No synthetic wind-speed time series is generated. The scenario ranges are analyst stress assumptions and not confidence intervals, annual forecasts, Monte Carlo estimates or observed cash flows.

Follow-up for investment use: obtain independently assessed P50/P90/P99 net annual energy production, project-side loss tree, actual PPA indexation and delivery boundaries, project CAPEX reconciliation, confirmed lender term sheets, operating-cost budget, debt reserve requirements, warranty/availability, annual debt schedule, real curtailment constraints and full project-finance model.