energy_methods.wind_installation#

Transparent daily turbine-installation and commissioning opportunity scenarios.

This is a project-planning sensitivity model, not offshore weather forecasting, asset dispatch, or a claim about any named project’s actual construction plan.

class energy_methods.wind_installation.InstallationSchedule(completion_days, duration_days, charter_vessel_days)[source]#

Bases: object

Daily-installation events; day 0 is the first illustrative campaign day.

Parameters:
  • completion_days (tuple[int, ...])

  • duration_days (int)

  • charter_vessel_days (int)

completion_days: tuple[int, ...]#
duration_days: int#
charter_vessel_days: int#
energy_methods.wind_installation.simulate_installation(turbines, *, vessel_start_days, workable_days, workable_days_per_turbine)[source]#

Install turbines with independent vessel crews and site-wide weather.

Each vessel accrues one unit of work on a workable day once available. Each turbine requires workable_days_per_turbine accumulated units on one vessel. Progress survives bad-weather days; vessels do not transfer partially completed turbine jobs. At most one turbine per vessel per day.

These simplified constraints ignore foundations, port loading, lifting, maintenance, cable laying and crew shifts; workload and site-wide weather are declared scenario inputs, not observed Dogger Bank conditions.

Parameters:
  • turbines (int)

  • vessel_start_days (Sequence[int])

  • workable_days (Sequence[bool])

  • workable_days_per_turbine (float)

Return type:

InstallationSchedule

energy_methods.wind_installation.commissioning_opportunity_mwh(schedule, *, project_capacity_mw, net_capacity_factor, horizon_days, grid_ready_day=0, commissioning_lag_days=0)[source]#

Conditional energy opportunity under progressive per-turbine commissioning.

Identical turbine AC ratings are assumed. A completed installation can generate no earlier than the next day, a uniform commissioning lag, and the common grid-ready day. This is an opportunity envelope, NOT measured generation, lost energy, contractual revenue or confirmed access to grid.

Parameters:
  • schedule (InstallationSchedule)

  • project_capacity_mw (float)

  • net_capacity_factor (float)

  • horizon_days (int)

  • grid_ready_day (int)

  • commissioning_lag_days (int)

Return type:

float